News
|
LCG, January 13, 2026--Oglethorpe Power today announced it has selected Kiewit Corporation through its subsidiary, The Industrial Company (TIC), as the Engineering, Procurement and Construction (EPC) partner for its new combined-cycle (CC), natural gas-fired power plant in Monroe County, Georgia. The new, 1,425-MW facility represents a capital investment of more than $3 billion. Commercial operation of the new generation capacity is planned to commence in 2029.
Read more
|
|
LCG, January 9, 2026--Meta today announced new, landmark agreements that will (i) extend and expand the operation of three existing nuclear power plants and (ii) drive the development of advanced nuclear technology. Meta's new agreements with Vistra, TerraPower, and Oklo follow Meta's request for proposals (RFP) issued last month. Meta expects these projects to deliver up to 6.6 GW of new and existing clean nuclear energy by 2035.
Read more
|
|
|
Industry News
Massachusetts Politicians Request Delay in SeaBrook License Extension
LCG, January 23, 2019--Two U.S. senators and a U.S. representative from Massachusetts jointly sent a letter to the Nuclear Regulatory Commission (NRC) last week opposing the NRC's decision to grant NextEra, the owner of the Seabrook, New Hampshire, nuclear power plant, a 20-year license extension and amendment later this month for the plant.
The NRC had recently announced plans to grant NextEra the extension of its operating license "on or about January 30," together with an amendment to the license regarding the presence of concrete degradation at the plant caused by alkali-silica reaction (ASR), which was discovered in 2009. The politicians requested a delay in the license amendment and renewal until after this summer's Atomic Safety Licensing Board hearing, which would include public input.
A NextEra representative stated, "Since 2011, the Nuclear Regulatory Commission has held more than a dozen public meetings, with the opportunity for members of the community to weigh in. Public meetings are an important part of the NRC's process, and we expect public conversations to continue. License renewal is important for protecting the role of Seabrook Station as a regional asset and a producer of clean, reliable and low-cost electricity for New England."
Commercial operations for the 1,250-MW pressurized water reactor (PWR) began in August 1990. The current license is due to expire March 15, 2030, and the license extension will enable carbon-free, electric generation from the nuclear facility into 2050.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|