LCG, September 12, 2025--Entergy announced yesterday that the Public Utility Commission of Texas (PUCT) approved Entergy Texas’ proposal to build two efficient natural gas-fired power plants to support the region’s rapid growth. The combined electric generating capacity of the two facilities, the Legend Power Station and the Lone Star Power Station, will add over 1,200 MW to the Southeast Texas power grid to support new customer demand, increase reliability and lower costs for all customers. Both facilities are scheduled to commence operations by mid-2028.
Read more
|
LCG, September 4, 2025--Puget Sound Energy (PSE) announced yesterday that phased construction has commenced on its 142-MW Appaloosa Solar Project, a utility-scale solar facility underway in southeastern Washington. The project is being built by Qcells EPC, who will serve as the module manufacturer and the engineering, procurement, and construction (EPC) solution provider. Construction is scheduled through 2026, and commercial operation is expected at the end of next year.
Read more
|
|
|
Industry News
Avangrid's 238-MW True North Solar Project Achieves Commercial Operation
LCG, March 27, 2025--Avangrid, Inc., a member of the Iberdrola Group, today announced that its True North Solar project, located in Falls County, Texas, has achieved commercial operation. The True North Solar project will deliver electricity into ERCOT and support Meta’s operations, including Meta's upcoming data center in neighboring Temple, its second data center in Texas.
Avangrid has operated in Texas for more than 15 years. With the addition of the 238-MW (321 MWdc) True North Solar project, Avangrid now has seven projects in Texas, with a combined installed capacity of nearly 1.6 GW. According to Avangrid, these projects represent over $2 billion in direct investment in the Texas.
“True North is a milestone project for Avangrid and we are proud to see it generating electricity for the Texas grid,” said Avangrid's CEO. “With a projected boom in data center construction over the next several years that will significantly increase energy demand, projects like True North are and will be vital to ensuring the resiliency and reliability of the Texas electrical grid. Furthermore, these facilities represent new sources of locally produced power that will support the state’s growing economy for decades to come."
Avangrid partnered with New Mexico-based Array Technologies to procure solar trackers for the project, which also includes over 488,000 solar panels. These solar trackers are key components to solar projects, as they move the solar panels to track the sun and maximize energy production.
Array’s CEO stated, “Array Technologies is proud to support Avangrid in delivering reliable, renewable energy through the True North solar project. Our domestically manufactured solar trackers are supporting American jobs and designed to optimize energy production, ensuring that projects like this can meet the growing demand for electricity. This milestone highlights the strength of American manufacturing and the critical role of innovative solar technology in powering the future.”
Avangrid worked with Black & Veatch to design and construct the solar project.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|