OPG Completes Darlington Nuclear Station Refurbishment Project Under Budget and Ahead of Schedule

LCG, February 2, 2026--Ontario Power Generation (OPG) announced today that construction on the four-unit Darlington Refurbishment project is now complete. Station staff are completing final testing, and the last unit is expected to return to service in the coming weeks. OPG stated that the overall project is currently four months ahead of schedule and $150 million under budget.

Read more

NERC's New Annual Assessment Shows Rapid Demand Growth Increasing Resource Adequacy Risks Across North America

LCG, January 30, 2026--The North American Electric Reliability Corporation (NERC) yesterday issued its 2025 Long-Term Reliability Assessment (LTRA) and infographic that spotlight intensifying resource adequacy risks throughout the North American bulk power system (BPS) over the next 10 years.

Read more

Industry News

Day-Ahead Market May Be Delayed in California

LCG, Nov. 1, 2002--A Federal Energy Regulatory Commission ruling that a day-ahead market be put in place in January by the California Independent System Operator will not be satisfied, the state grid operator has told the federal agency.

According to the ISO, the timetable imposed by the FERC will create liability exposure and the possibility of a poorly designed set of market rules. The FERC ruled in early October that it would not allow a proposed delay of a day-ahead market for CAISO, until mid-2003. The ISO has run an hour-ahead market, but not a day-ahead market, which was formerly the responsibility of the defunct California Power Exchange.

The FERC believes that generation resources and transmission capacity can be matched more dependably with a day-ahead market. In order to implement the FERC's deadline, the ISO will need to relax restrictions concerning submittals of balanced schedules, which indicate the providers and consumers making up each side of a transaction. "Following the Oct. 11 order, the California ISO has re-examined the feasibility of relaxing the balanced schedule requirement and the market separation rule and conlcuded that it is impossible to do so by Jan. 31, 2003," the grid operator stated.

In expressing the ISO's attitude towards the January deadline, ISO spokesman Gregg Fishman indicated that a more comprehensive, complex set of provisions for the day-ahead and hour-ahead markets the ISO will be required to implement at an as-yet-unspecified date should be its goal, without the ISO's having to rush to an intermediate version before the ISO is ready. "If you are making plans to remodel your entire kitchen in the spring, why are you spending time painting it in the fall," Fishman said.
Copyright © 2026 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service