OPG Completes Darlington Nuclear Station Refurbishment Project Under Budget and Ahead of Schedule

LCG, February 2, 2026--Ontario Power Generation (OPG) announced today that construction on the four-unit Darlington Refurbishment project is now complete. Station staff are completing final testing, and the last unit is expected to return to service in the coming weeks. OPG stated that the overall project is currently four months ahead of schedule and $150 million under budget.

Read more

NERC's New Annual Assessment Shows Rapid Demand Growth Increasing Resource Adequacy Risks Across North America

LCG, January 30, 2026--The North American Electric Reliability Corporation (NERC) yesterday issued its 2025 Long-Term Reliability Assessment (LTRA) and infographic that spotlight intensifying resource adequacy risks throughout the North American bulk power system (BPS) over the next 10 years.

Read more

Industry News

Duke and AEP's 765-kV Transmission Project in Indiana Gains Momentum

LCG, December 9, 2011--Duke Energy announced yesterday that Pioneer Transmission, a 50-50 joint venture formed by Duke Energy and American Electric Power (AEP), will begin engineering, permitting and siting activities next year on the 765-kV Greentown-New Reynolds project, designated yesterday as one of 17 Multi-Value Projects (MVPs) included in the Midwest ISO (MISO) Transmission Expansion Plan. The Plan is designed to enhance regional power system reliability, improve market efficiency, enable public policy mandates and facilitate the integration of new generation resources, including renewable energy.

The proposed transmission line will be constructed in Indiana and extend approximately 66 miles to connect the existing Greentown substation (east of Kokomo) with a new substation called New Reynolds (north of Lafayette). The specific route has yet to be finalized. The estimated cost of the 66-mile Greentown-New Reynolds project is $245 million. Pioneer Transmission will build and own the New Reynolds substation to handle the interconnection of multiple power line voltages at this location.

Pioneer Transmission plans to file a petition for public utility status with the Indiana Utility Regulatory Commission by year-end.

The project is part of a larger, 240-mile transmission project in Indiana originally proposed by Pioneer Transmission in 2008 and estimated to cost $950 million. The larger project will be evaluated by PJM and MISO next year.
Copyright © 2026 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service