PUC of Texas Approves Entergy Texas' Plans to Build Over 1,200 MW of Gas-Fired Capacity

LCG, September 12, 2025--Entergy announced yesterday that the Public Utility Commission of Texas (PUCT) approved Entergy Texas’ proposal to build two efficient natural gas-fired power plants to support the region’s rapid growth. The combined electric generating capacity of the two facilities, the Legend Power Station and the Lone Star Power Station, will add over 1,200 MW to the Southeast Texas power grid to support new customer demand, increase reliability and lower costs for all customers. Both facilities are scheduled to commence operations by mid-2028.

Read more

Puget Sound Energy Starts Construction on 142-MW Appaloosa Solar Project in Washington

LCG, September 4, 2025--Puget Sound Energy (PSE) announced yesterday that phased construction has commenced on its 142-MW Appaloosa Solar Project, a utility-scale solar facility underway in southeastern Washington. The project is being built by Qcells EPC, who will serve as the module manufacturer and the engineering, procurement, and construction (EPC) solution provider. Construction is scheduled through 2026, and commercial operation is expected at the end of next year.

Read more

Industry News

PacifiCorp Weighs Options for Coal-fired Power Plants

LCG, April 27, 2012--PacifiCorp, a unit of MidAmerican Energy Holdings, announced yesterday that future federal and state environmental requirements for its coal fleet would cost over $1 billion in coming years. As a result, its fleet is expected to reduce coal consumption and increase reliance on natural gas.

The company is evaluating a number of options at its coal plants. To comply with state and federal air quality regulations to improve visibility in national parks and wilderness areas, the company has concluded that the preferred option is to convert the 330-MW Naughton 3 coal-fired unit in Wyoming to low-cost natural gas, rather than installing new emission controls for coal that will be required after 2014.

In Utah, PacifiCorp is evaluating compliance options in response to the utility mercury and air toxics standards (MATS) at its 172-MW Carbon coal-fired plant. At this time, the company has determined the lowest cost option for the aging Carbon plant is to decommission the facility, although additional options are still be being pursued.

PacifiCorp is also developing other gas-fired facilities, including the construction of a 637-MW natural gas-fired, combined cycle plant at its Lake Side facility south of Salt Lake City. The new facility is scheduled to commence operation in the summer of 2014.
Copyright © 2025 LCG Consulting. All rights reserved. Terms and Copyright
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
Uniform Storage Model
A Battery Simulation Model
UPLAN-ACE
Day Ahead and Real Time Market Simulation
UPLAN-G
The Gas Procurement and Competitive Analysis System
PLATO
Database of Plants, Loads, Assets, Transmission...
CAISO CRR Auctions
Monthly Price and Congestion Forecasting Service