LCG, March 13, 2026--The Southwest Power Pool (SPP) announced yesterday that leaders from the participating organizations voted unanimously to proceed as planned with expanding its regional transmission organization (RTO) services into the Western Interconnection. SPP sees the decision to proceed as planned as a strong signal of confidence as SPP and its partner utilities prepare for this key milestone, which will occur overnight between March 31 and April 1.
Read more
|
|
LCG, March 6, 2026--Entergy yesterday announced approximately $5 billion in total savings for 2.3 million customers in Arkansas, Louisiana and Mississippi resulting from data center customer agreements in those states. Entergy, which completed its first data center customer agreement in 2024, projects the customer savings over the next 20 years and after the regulatory approval or acknowledgement of the public service commissions in those states.
Read more
|
|
|
Industry News
Court Ruling Supports Dominion's Plans for Exports at Cove Point LNG Terminal
LCG, January 9, 2013--In a court ruling made public on January 4, Dominion Resources Inc. retains the right to export liquefied natural gas (LNG) from its Cove Point, Maryland, facility on the Chesapeake Bay. The Circuit Court Judge rejected arguments by the Sierra Club that such exports violated a 2005 agreement. With the court ruling, Dominion announced it will proceed with engineering, marketing and regulatory review processes to enable LNG exports from the Cove Point site. Dominion expects the liquefaction project to cost between $2.5 billion and $3.5 billion.
Dominion acquired the Cove Point facility from Williams in 2002 and began importing LNG via ships in the summer of 2003. In 2009, Dominion finished an expansion project that increased Cove Point's storage and production capacity by nearly 80 percent. With the drop in natural gas prices and ample gas supplies in North America, Dominion has reversed course and plans to modify the site to enable LNG exports.
The Circuit Court ruled that Dominion Cove Point's agreement with environmental agencies allows it to build liquefaction facilities inside the plant's fenced area and export LNG. The Sierra Club had maintained Dominion needed its permission to build the facilities. Dominion's president and CEO stated, "Dominion has made considerable progress towards a project that will bring jobs and revenues to the national and local economies. We have received support from business, labor, government, community and environmental groups for a major construction project that would bring great benefits to many people. We look forward to working with the Sierra Club and other involved environmental groups to continue the outstanding record of environmental cooperation at Dominion Cove Point." Last June Dominion filed a request with the Federal Energy Regulatory Commission (FERC) to start the pre-filing process in anticipation of filing an application this year.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|