LCG, July 24, 2025--The U.S. Department of Energy (DOE) today announced the next steps in the Trump administration’s plan to accelerate the development of AI infrastructure by using Federal lands to lower energy costs and help power the global AI race, as previously outlined in President Trump’s Executive Orders on Accelerating Federal Permitting of Data Center Infrastructure, Deploying Advanced Nuclear Reactor Technologies for National Security, and Unleashing American Energy.
Read more
|
LCG, July 22, 2025--Enbridge Inc. (Enbridge) today announced that it has reached a final investment decision on the Clear Fork solar project located near San Antonio, Texas. Meta Platforms, Inc. (Meta), has signed a long-term contract for all of the renewable power generated from the 600-MW project.
Read more
|
|
|
Industry News
Southern's Kemper County IGCC Project Now Targets Completion in Fourth Quarter 2014
LCG, October 31, 2013--Southern Company announced yesterday a delay in the schedule to begin operations of its Kemper County coal project that is currently under construction by its subsidiary, Mississippi Power.
Southern Company now expects subsidiary Mississippi Power's Kemper County project to be complete in the last quarter of 2014 and the costs to exceed $4 billion. Southern Company earnings for the three months and nine months ended September 30, 2013, include after-tax charges of $93 million and $704 million, respectively, related to increased cost estimates for the construction of the Kemper County project.
Plant Ratcliffe, located in Kemper County, Mississippi, is a 582-MW IGCC (Integrated Gasification Combined Cycle) project. In December 2010, Mississippi Power held the ground breaking ceremony for the project, and the estimated cost of the project was then $2.4 billion. Operations were targeted to commence in 2014. In April 2013, the project cost was estimated to be over $3.2 billion, with a May 2014 deadline to start service to retain certain tax incentives.
The IGCC project is designed to convert coal into synthetic gas, which will then be burned in a combined cycle system. The project's carbon capture system will capture at least 65 percent of the CO2 that results from combustion of the syngas. The captured CO2 will be transported via pipeline and used for enhanced oil recovery (EOR). The project is located adjacent to the fuel source, lignite.
In the third quarter of 2013, the Kemper County project achieved several major construction milestones, including the first fire of the facility?s two combustion turbines, which were completed August 28 and September 4. In late September, testing on the steam turbine was completed, which allows it to be synced to the grid in early October.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|