LCG, April 9, 2025--Duke Energy announced yesterday its submission of a subsequent license renewal (SLR) application to the U.S. Nuclear Regulatory Commission (NRC) for the Robinson Nuclear Plant, a 759-MW nuclear unit located near Hartsville, South Carolina. The application requests extending the plant's operations for an additional 20 years.
Read more
|
LCG, April 8, 2025--Gemma Power Systems (“Gemma”), a wholly owned subsidiary of Argan, Inc. (“Argan”), has received a notice to proceed on its previously announced engineering, procurement and construction (“EPC”) services contract with Sandow Lakes Energy Company, LLC (“SLEC”) for a 1.2-GW power plant in Lee County, Texas. Construction of the natural gas-fired, combined cycle facility is scheduled to commence this summer, with an expected project completion date in 2028
Read more
|
|
|
Industry News
WPS Files Application with the Public Service Commission of Wisconsin to Build Combined Cycle Facility at Fox Energy Center
LCG, January 22, 2015--Wisconsin Public Service Corp. (WPS) submitted its application for permission from the state Public Service Commission to install a 400-MW natural gas-fired, combined-cycle generating unit at the Fox Energy Center in Kaukauna, Wisconsin. The estimated cost of the project is $517 million. Construction is anticipated to begin late in the spring of 2016.
The existing Fox Energy Center hosts a 593-MW combined cycle generating facility that began commercial operation in December 2005. WPS originally purchased the power generated from the facility. In March 2013, WPS acquired the dual fuel (natural gas and oil) facility for a total purchase price of $440 million from Fox Energy Center LLC, owned by subsidiaries of Tyr Energy, Inc. and General Electric.
Late in 2013, WPS announced a need for an additional 400-500 MW of electric generating capacity by 2019. Alternatives considered were to purchase power from other energy suppliers, buy an existing or new generating facility, or add another natural gas-fueled generator at the Fox Energy Center.
WPS also operates coal-fired power plants in Wausau and Green Bay, and these coal-fired plants may be taken out of service to avoid the need to invest in equipment and controls to meet increasingly stringent environmental regulations.
A WPS spokesperson stated, "The studies say this is the best thing to do to meet our needs in 2019. It's the right site, it's the right time, it makes great sense.We are able to take advantage of existing cooling water and intake structures, as well as the electric transmission facilities and natural gas pipeline already in place at the site."
The Public Service Commission hearings are planned during the spring and summer, with a ruling likely by year-end.
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|