News
|
LCG, April 30, 2026--OG&E, the operating subsidiary of OGE Energy Corp., announced today that it will power three new data centers that Google announced in Muskogee and Stillwater, Oklahoma last year. As part of the agreement, Google will also make power generation capacity available from two solar facilities in Stephens and Muskogee Counties that are currently under construction. The data centers and associated Electric Service Agreements are expected to provide economic growth for local communities and the state, contribute to grid stability, and benefit OG&E's current customers.
Read more
|
|
LCG, April 29, 2026--Graphic Packaging Holding Company today announced a virtual power purchase agreement (VPPA) with NextEra Energy Resources, LLC. With the VPPA agreement, NextEra Energy Resources plans to build the Selenite Springs Energy Center, a 250-MW solar energy facility in West Texas, and Graphic Packaging will be the sole buyer of the facility's renewable energy attribute certificates. Graphic Packaging, a global provider of sustainable consumer packaging, expects the agreement to cover approximately 43 percent of its 2025 electricity usage in the U.S. and Canada. The agreement will advance Graphic Packaging's commitment to source renewable electricity and reduce its greenhouse gas (GHG) emissions.
Read more
|
|
|
Industry News
Dominion Announces Plans to Construct 1,600-MW Natural Gas-fired Power Plant in Virginia
LCG, April 8, 2015--Dominion Virginia Power recently announced its proposal to construct a 1,600-MW natural gas-fueled power station in Greensville County, Virginia. The facility, which is estimated to cost of over $1 billion, is scheduled to commence operations in 2019. The additional electric generating capacity is needed to serve the growing electric demand in the region.
Dominion Virginia Power plans to submit its application for a Certificate of Public Convenience and Necessity (CPCN) to the State Corporation Commission (SCC) in July. Construction would begin in mid- 2016, subject to SCC and environmental approvals.
Last November Dominion issued a request for proposals (RFP) to begin delivery of electricity in the 2019/2020 timeframe. After evaluating the proposals, Dominion decided that constructing the power station in Greensville County would be the most beneficial to its customers.
The proposed combined-cycle facility design calls for three gas-fired combustion turbines and a steam turbine. The facility will be built on an 1,143-acre site that straddles the Greensville/Brunswick County line, with 740 acres in Greensville County. The applications also seek to have the site approved for the construction of a future large-scale solar project.
Natural gas delivery to the new power plant will be via a Williams' Transco pipeline extension to the site and the proposed Atlantic Coast Pipeline (ACP) that will cross the station property when that pipeline is built. The two interconnections are desired so as to improve operational reliability by providing flexibility and redundancy in procuring the station's fuel supply and providing fuel supply diversity.
Dominion is already constructing a 1,300-MW combined-cycle power station in Brunswick County that is approximately 58 percent complete.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|