LCG, March 17, 2026--Oklo Inc. (Oklo) today announced that it has signed a U.S. Department of Energy (DOE) Other Transaction Agreement (OTA) to support the design, construction, and operation of Oklo’s first reactor, the Aurora powerhouse at Idaho National Laboratory (INL) under DOE’s Reactor Pilot Program (RPP). The DOE Idaho Operations Office subsequently approved the Nuclear Safety Design Agreement (NSDA) for the fast-fission power plant, and Oklo immediately requested DOE commence review of its Preliminary Documented Safety Analysis (PDSA).
Read more
|
|
LCG, March 13, 2026--The Southwest Power Pool (SPP) announced yesterday that leaders from the participating organizations voted unanimously to proceed as planned with expanding its regional transmission organization (RTO) services into the Western Interconnection. SPP sees the decision to proceed as planned as a strong signal of confidence as SPP and its partner utilities prepare for this key milestone, which will occur overnight between March 31 and April 1.
Read more
|
|
|
Industry News
TVA Requests Issuance of License for Watts Bar Unit 2
LCG, August 20, 2015-The Tennessee Valley Authority (TVA) submitted documentation to the Nuclear Regulatory Commission (NRC) notifying them that construction of the Watts Bar Unit 2 nuclear reactor, located approximately 50 miles northeast of Chattanooga, Tennessee, is substantially complete.
TVA further provided a list of remaining key activities to complete prior to operations and requested that an operating license be issued for the unit. TVA's submittal of its "substantially complete" letter is a major construction and licensing milestone for the project.
The original construction on Watts Bar 2 started over 40 years ago in 1972. However, when load growth forecasts dropped in 1988, the unit was deferred. When Watts Bar 1 began commercial operations in May 1996, it became the last commercial nuclear unit in the United States to come on-line. Construction on Unit 2 resumed in 2007. The capacity of Unit 1 and Unit 2 are 1,100 MW and 1,150 MW, respectively.
TVA must show that construction is substantially complete, that the facility will operate according to the license, and that there is assurance the unit will have no adverse effect on public health and safety prior to the NRC issuing an operating license. The NRC staff is working towards supporting an operating license decision in 2015.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|