News
|
LCG, March 13, 2026--The Southwest Power Pool (SPP) announced yesterday that leaders from the participating organizations voted unanimously to proceed as planned with expanding its regional transmission organization (RTO) services into the Western Interconnection. SPP sees the decision to proceed as planned as a strong signal of confidence as SPP and its partner utilities prepare for this key milestone, which will occur overnight between March 31 and April 1.
Read more
|
|
LCG, March 6, 2026--Entergy yesterday announced approximately $5 billion in total savings for 2.3 million customers in Arkansas, Louisiana and Mississippi resulting from data center customer agreements in those states. Entergy, which completed its first data center customer agreement in 2024, projects the customer savings over the next 20 years and after the regulatory approval or acknowledgement of the public service commissions in those states.
Read more
|
|
|
Industry News
ESC Announces Open Solicitation Process for 1,000 MW HVDC Empire State Connector Transmission Project
LCG, November 28, 2017--Empire State Connector Corp. (ESC) announced yesterday the start of an Open Solicitation process for interested parties to reserve transmission capacity on the proposed 265-mile, 1,000 MW fully buried Empire State Connector (ESC) high voltage direct current (HVDC) electric transmission line designed to deliver electricity from non-carbon emitting resources in upstate New York to loads in New York City. The target in-service date of the project is 2022.
The Open Solicitation represents the next step in the development of the ESC, following the Federal Energy Regulatory Commission (FERC) order authorizing ESC to sell transmission rights and services on its proposed merchant transmission project at negotiated rates. London Economics International will serve as the independent solicitation manager for the Open Solicitation. Non-binding Expressions of Interest will be accepted until December 22, 2017.
The ESC will follow a unique underwater route through the Erie Canal and Hudson River so as to have no visual impact and low environmental impact. Upstate New York energy will be collected at a converter station built near Utica, where the electricity will be converted from AC to DC and transmitted via two six-inch diameter non-fluidized solid-state cables over 260 miles directly into the heart of New York City, where the electricity will be converted back to AC and injected into the grid.
The project has completed the New York Independent System Operator (NYISO) interconnection feasibility study. According to ESC, preliminary engineering, environmental pre-feasibility study, route surveys and routing assessments have all been completed. A public outreach program is fully underway and the ESC plans to file its Article VII application with the PSC by the end of the year.
The ESC will support New York State's Clean Energy Standard (CES) that is designed to reduce carbon emissions from the state's power suppliers.
ESC's CEO stated, "This project perfectly complements the state's and the City's energy, economic and environmental policy goals. It creates significant upstate economic growth, spurs the development and use of clean, renewable energy, helps better tie together New York's massive electric grid with highly-controllable transmission technology and delivers low carbon energy into New York City."
ESC filed its application with the FERC for authority to negotiate agreements with customers for transmission service on the ESC in April 2016, when the construction cost was estimated to be approximately $1.5 billion.
|
|
|
|
UPLAN-NPM
The Locational Marginal Price Model (LMP) Network Power Model
|
|
|
UPLAN-ACE
Day Ahead and Real Time Market Simulation
|
|
|
UPLAN-G
The Gas Procurement and Competitive Analysis System
|
|
|
PLATO
Database of Plants, Loads, Assets, Transmission...
|
|
|
|
|